Well point dewatering system cost in Sanford and Central Florida

A well point dewatering system around Sanford, FL costs $3,000 to $8,000 to set up on a utility trench of about 100 feet, and $8,000 to $30,000 on a building pad or foundation excavation. Pump rental with fuel and maintenance adds $1,900 to $3,300 for every four weeks the system runs.

Those are the numbers we quote from, and they come straight off our published dewatering cost guide. Most national pages on this topic stop at "it depends, call for a quote". The rental houses say the same thing. This page shows the ranges, what sits inside them, and what moves a job up or down. If you want the system itself explained first, start with the wellpoint dewatering systems page.

How much does a well point dewatering system cost?

It costs a one time setup price plus a recurring pump rental, and the setup depends on what you are digging. Here is the full well point price list for Seminole County and the north Orlando metro.

JobTypical rangeCharged
Sewer or water main trench, first 100 ft of header$3,000 to $8,000per setup
Each additional 100 ft of trench$2,500 to $7,500per 100 ft
Building pad, footer or foundation excavation$8,000 to $30,000per setup
Pump rental with maintenance and fuel$1,900 to $3,300per 4 weeks
Deep staged cuts and large civil work$30,000 to $100,000per project

A shallow cut with slow inflow may not need well points at all. A sump and open pumping setup runs $1,500 to $5,000 and is the right tool when the hole is only a couple of feet into groundwater and the soil is firm.

What is included in a well point setup price?

The setup price covers getting the water table down and keeping the discharge legal. On our jobs that means six things.

  1. A look at your plans, cut depth and boring log to set point spacing and pump size.
  2. Jetting the well points into the ground along the trench or around the pad.
  3. The header pipe, swing joints and a vacuum assisted pump, connected and primed.
  4. Discharge hose or pipe to the outfall, with settling and turbidity control.
  5. The FDEP dewatering generic permit notice, prepared and filed.
  6. Pulling the system when you backfill.

Ask any contractor which of those six are in their number. A cheap quote that leaves out discharge control or the permit notice is not cheap by the end of the job.

What does it cost per month to keep the pumps running?

Budget $1,900 to $3,300 per four week block for the pump, with maintenance and fuel in that price. Where you land depends on pump size (4 inch, 6 inch or 8 inch), diesel or electric drive, and a standby pump staged on site. Rental companies bill in 28 day cycles, not calendar months, so a ten week job is three blocks. Count it that way in your bid.

Three sample budgets

These add up lines from the table above. They are budget math for estimators, and your own job gets its own number once we see the site.

JobWhat is added upBudget range
100 ft sewer lateral trench, pumped for four weeksOne trench setup plus one rental block$4,900 to $11,300
300 ft storm pipe run, pumped for four weeksOne trench setup, two more 100 ft sections, one rental block$9,900 to $26,300
Lift station pit or building pad, pumped for eight weeksOne pad setup plus two rental blocks$11,800 to $36,600

Why is one well point quote twice the price of another?

Usually because the two contractors assumed different ground. Six things decide where a job sits inside its range.

  1. Depth below the water table. Every foot of drawdown means more pumping. A 6 foot water line trench sitting two feet into groundwater prices near the bottom of the range. A 12 foot gravity sewer cut prices near the top.
  2. The 15 foot suction limit. One stage of well points pulls the water table down about 15 feet. Go deeper and a second header gets set on a bench partway down, which roughly doubles the system on that deep section.
  3. Soil and point spacing. Clean sand lets the points spread toward 6 feet apart. Fine sugar sand near the lakes needs them closer to 3 feet, so the same 100 feet of header carries almost twice the points. Organic muck drains slowly and clogs screens.
  4. Distance to legal discharge. Fifty feet of hose to a vegetated swale costs very little. Several hundred feet of pipe with a settling tank and turbidity control is a real line item.
  5. Weeks on the pump. The setup is paid once. Rental repeats every four weeks until backfill, so a slipped inspection or a late pour shows up here.
  6. Time of year. June through September lifts the water table across Central Florida. The same trench can land low in the range in April and mid range in August.

A contractor who has not seen your boring log has to guess at half that list, and the guess gets padded. Send the geotech report with the request and the padding goes away.

Is the discharge permit part of the cost?

On our setups, yes. Preparing and filing the notice is in the setup price. Florida regulates pumped groundwater that leaves a construction site, and the state's construction dewatering FAQ from Florida DEP explains when a site can discharge under its construction stormwater coverage and when it needs the separate dewatering generic permit. Very large or long extractions can also need a consumptive use review from the St. Johns River Water Management District. That review is scoped and named separately before work starts. Our permit guide sorts out which rule applies to which job.

How to get a firm number

Every site is different, so the firm price comes from a call. Have four things ready and it goes fast.

  1. The site address.
  2. How deep the cut goes, and how long the trench or how big the pad is.
  3. A boring log or geotech report if one exists.
  4. Your dig date and how many weeks the hole stays open.

Call (321) 415-8927 or send the form below. We answer with a range off the published table and name what is driving it, usually the same day.

Published pricing · FDEP discharge permits handled · Based in Sanford